Golden Grove is a Volcanic Hosted Massive Sulphide deposit consisting of Gossan Hill and Scuddles underground mine operations. Due to ground conditions and the depth of existing and future development, cemented backfill is considered essential to maintain an acceptable extraction rate and recovery. Therefore, 29 Metals decided to install a modular backfill plant, capable of supplying a flow rate of 120 m3 /h of paste, supplied by Quattro Project Engineering.
NewPro was engaged for project management, engineering support and commissioning service of the paste fill plant.
Client: 29 Metals
Completion Date : December 2022